28 January 2019
Use Case Points.
by NGUYEN DINH QUANG
Use Case Points (UCP)
-
Unadjusted Use Case Weight (UUCW)

-
Unadjusted Actor Weight (UAW)

-
Technical Complexity Factor (TCF)
TCF = 0.6 + (TF/100)

-
Environmental Complexity Factor (ECF)
ECF = 1.4 + (-0.03 x EF)

-
Corresponding interpolation values (S) of Environmental Complexity Factor (ECF)

-
Experience Stability Estimate (ES)
\[ES = \sum_{i=1}^8 S_i\]

-
Unadjusted Use Case Weight (UUCW)
UUCW = (Total No. of Simple Use Cases x 5) + (Total No. Average Use Cases x 10) + (Total No. Complex Use Cases x 15)
-
Unadjusted Actor Weight (UAW)
UAW = (Total No. of Simple Actors x 1) + (Total No. Average Actors x 2) + (Total No. Complex Actors x 3)
-
Use Case Points (UCP)
UCP = (UUCW + UAW) x TCF x ECF
-
Estimate Effort (EE)
EE = AUCPxP (Hours)
-
Step by step Use Case Points Methods



-
Technical Complexity Factor

-
Environmental Complexity Factor


Latest Posts
tags: software estimation - use case points